From 1 January 2027, a new Abu Dhabi hospital that meets two of three tests must have underground protected capacity designed in from day one. DoH has not yet said what that space must contain, or what it will cost.
DoH Circular 202/2026, dated 9 October 2026, requires underground protected healthcare capacity in any new Abu Dhabi hospital that meets two of three tests: critical acute or tertiary services, 150 or more planned licensed beds, or essential regional cover with no comparable acute hospital within about 100 km. It applies to new licence applications from 1 January 2027, must be designed in from the first stage, and may double as parking if it converts in time. The technical standard is due by the same date and has not been issued. Projects already in licensing are decided case by case. For a developer, operator or lender, that is an unpriced capex line and a design-stage licensing gate.
What a board member needs before the next meeting on this.
- Two of three tests decide scope. Critical acute or tertiary services, 150 or more planned licensed beds, and essential regional cover with no comparable acute hospital within about 100 km. Meet any two and the requirement applies to a new licence application filed on or after 1 January 2027.
- It has to be in the first design. The circular requires the capacity from the initial development stage and says applicants should not rely on modifying an approved hospital design later. DoH may ask for evidence at licensing and approval stages.
- The specification is pending. DoH will issue the technical and engineering requirements by 1 January 2027, the same date the rule starts. Size and function are set by DoH in proportion to services, beds, emergency role and risk.
- Filing early is no safe harbour. Projects already under development or in licensing on the effective date are assessed case by case. Parking may double as the protected area, subject to DoH approval and conversion within the activation timeframe.
The Department of Health in Abu Dhabi issued Circular No. 202/2026, dated 9 October 2026 and listed on its index on 12 October as USO/202/2026, to all healthcare providers and applicants for new hospital licences in the emirate (DoH circulars).
It requires underground protected healthcare capacity in new hospital developments and applies to new hospital licence applications submitted on or after 1 January 2027 (DoH Circular 202/2026). That is 84 days from the circular's date, on our count. The circular contains no cost figure, and DoH has not yet said what the protected space must contain. The obligation is fixed. Its size is still open.
Two of three tests bring a hospital into scope
The requirement applies where a proposed hospital meets at least two of three criteria: it is planned to provide critical acute or tertiary services, including Level I or II trauma, neurosurgery, cardiovascular and comparable high-acuity surgery; it has a planned licensed inpatient capacity of 150 beds or more; or it gives essential acute cover to a regional or rural area with no comparable acute hospital within approximately 100 kilometres (DoH Circular 202/2026).
On our reading, a 150-bed general hospital in Abu Dhabi city with a cardiac service is in scope, and a 140-bed cardiac centre on the same street is outside it unless DoH treats its location as remote.
The service list is written as "including, but not limited to", and the remote test defers to DoH criteria for rural areas that the circular does not reproduce, so two of the three thresholds carry DoH discretion.
The cost lands at the design stage
Where the requirement applies, the protected capacity must be built into the hospital's planning and design from the initial development stage, and applicants are told to account for it from the earliest stages of site selection, architectural design, engineering planning and capital development (DoH Circular 202/2026).
The circular adds that applicants "should not rely on subsequent modification of an approved hospital design", and that DoH may ask for evidence of compliance at stages of the licensing and approval process. An underground level is a structural decision that changes excavation, foundations and programme. On our reading, a scheme whose design is frozen without it carries a licensing risk that cannot be fixed later at a price anyone would choose.
Get the instruments that touch your licence, assessed, as they are issued. See Regulatory Watch
The specification arrives on the day the rule starts
DoH will issue detailed technical and engineering requirements for design, construction, equipping, commissioning, activation, operation and maintenance by 1 January 2027, which may cover structural protection, emergency power, ventilation, medical gases, water, fire safety, communications, infection control, surge configuration and activation times (DoH Circular 202/2026). That specification is pending; once issued, it becomes part of DoH's hospital licensing requirements.
The deadline for the standard is the date the obligation begins, so a hospital designed this quarter for filing in January is being designed to a document that has not been published. Size is open too. The circular makes capacity proportionate to licensed services, bed count, emergency role and risk profile, and leaves DoH to decide whether the space supports continuity of existing care, emergency admission, or both.
Parking can count if it can convert
Subject to DoH approval and building, civil defence and safety rules, the protected area may serve non-clinical uses such as parking during normal operations, provided it can be converted to its emergency clinical function within the required activation timeframe (DoH Circular 202/2026). Normal use must not compromise structural protection, emergency utilities, medical gas and ventilation where applicable, infection control or readiness for activation.
That is the main lever on cost. On our reading, a basement car park already in the scheme carries part of the excavation, and the increment is the protection, the services and the conversion capability. The activation timeframe is one of the items the pending standard will set.
Filing in december does not settle it
Projects already under development or within the licensing process on the effective date are assessed by DoH case by case, taking account of their stage of design, approval and construction (DoH Circular 202/2026). There is no safe harbour for early filers. For a buyer or lender, every large Abu Dhabi hospital in the pipeline carries an open question until DoH answers it in writing.
Until the standard is issued, a capex model should carry the line as a range with stated assumptions: a base case in which a planned basement car park is upgraded to dual use; an upside in which DoH assigns only the continuity function, for existing patients and surge, with no emergency admission function; and a downside in which DoH requires an emergency admission function on a dedicated level. We put no figure on any of them. The instrument gives none, and an invented benchmark would mislead the one reader who knows the build cost.
Four questions before an Abu Dhabi hospital design is frozen
- Which of our Abu Dhabi hospital projects meets two of the three tests, counting planned licensed beds rather than built beds?
- For any project already in design or licensing, has DoH told us in writing whether the requirement applies?
- What range does the capex model carry for protected capacity before the technical standard is issued, and what assumption sits behind the downside case?
- If our design is already approved, what would adding an underground protected level now cost in time and money, given DoH says not to rely on modifying an approved design?
The Monday work is short. Score every Abu Dhabi hospital project against the three criteria, using planned licensed beds. For any project in design or licensing, write to DoH's Healthcare Quality Sector at HCPS@doh.gov.ae and ask whether the requirement applies. Hold design freeze where the answer is open, and put the protected-capacity range into the capex model and the lender's base case before the January filing window. Testing a hospital case before a rule like this reshapes it is the work of our feasibility study practice.
This brief covers one instrument. The UAE healthcare regulatory tracker carries the full set — DoH, DHA, EDE and the other emirates — with what each one changes and when it takes effect.