Licensing Readiness PackMost licensing delays are sequencing errors. The pack sets the sequence before you sign a lease.

A clinic signs a lease, then learns the premises need a layout approval that takes the fit-out budget with it. A manufacturer files a product with the Emirates Drug Establishment before the importer is appointed and loses four months. The readiness pack is the sequence for your facility or product, with every document, fee and approval in the order the regulator expects it, written by the people who will lodge the application if you ask them to.

Fixed fee. AED 25,000 for a single facility or product family; up to AED 60,000 for a group, a multi-emirate footprint or a product portfolio. Scoped in writing before we start.

Who engages this

Doctors and investors opening a first clinic or day-surgery centre in Dubai, Abu Dhabi or the Northern Emirates. Operators adding a site under a second regulator. Pharmaceutical and device companies registering a first product with the Emirates Drug Establishment, or a UAE-registered product with the SFDA in Saudi Arabia. International entrants deciding between a free zone and the mainland before anything is signed.

The work

What this practice takes on.

01

The Sequence

Entity, premises, facility licence, clinician licences and payer empanelment, in the order each regulator demands.

02

The Document List

Every document, attestation and translation, with who issues it and how long it takes to obtain.

03

Fees and Timeline

Government fees stated from the regulator's own schedule, and a dated timeline to first billed claim.

04

Premises and Layout

What the layout approval will test, before the fit-out contractor is paid.

05

Product Registration Route

EDE verification, abridged or full pathway, importer requirements, and the SFDA route for Saudi Arabia.

06

Filing, If You Want It

The pack stands alone. If you would rather we lodged the application, the pack fee is credited against that work.

On a mandate

An orthopaedic surgeon and his investor had agreed heads of terms on a Jumeirah villa for a day-surgery centre. The pack showed the premises could not meet the DHA day-surgery standard without structural work the landlord would not permit, and that the specialty they planned required an approval the surgeon's licence category did not yet carry. They walked away from the lease, took a purpose-built unit in Dubai Healthcare City instead, and billed their first claim fourteen weeks after signing, inside the timeline the pack had set.

Questions

What clients ask first.

Why pay for a pack when setup agents give the steps away?

The free steps are generic and often out of date. The pack is written for your facility type, specialty, emirate and licence category, by a regulatory team that lodges these applications, and it is dated. The cost of a wrong sequence is usually a lease payment or a month of lost billing, which is many times the fee.

How long does the pack take?

Ten business days for a single facility or product family, up to fifteen for a group or portfolio. It begins with a scoping call so that the pack answers your situation and not a standard one.

Do you cover Saudi Arabia?

For products, yes: the SFDA verification and abridged pathways for a product already approved in a reference market, and the authorised representative requirement. For facilities in Saudi Arabia we work with a local partner and say so in the pack.

Is the fee credited if you file the application for us?

Yes, in full. The pack is the first part of the filing work, so you do not pay for it twice.

If you are about to sign a lease, appoint a distributor or file a dossier, get the sequence first.

Engagement · Limited mandates

Choosing who advises you is itself a strategic decision.

We take a limited number of mandates at any time. If you are working a decision that needs independent counsel, start with a conversation.